Oldbury Generator Transformer On The Move

$
0
0

As part of a decommissioning programme, a large item of plant has been removed for the first time.

The generator transformer played a vital role during the operation, it converted the electrical output from the station to make it suitable for distribution
to homes and businesses across the UK.

Mike Heaton, Oldbury Site Director, said: "The completion of this project safely and ahead of schedule marks the first
successful step in consigning major waste items from Oldbury. 

"Income from recycling the scrap metal will help pay for the UK
nuclear decommissioning programme."

The transformer weighs in at over 170 tonnes, contains more than 30 tonnes of copper and around 120 tonnes of steel,
measuring over four metres high, nine metres long and four metres wide.

Following detailed preparation work, the transformer was transferred to Sharpness Docks on a specialist low-loader
where it will be sent for recycling